A wholly controlled, fully permitted Tanzanian gold development project held under Mining Licence ML 538/2015. Initial spot repairs along the 14 km Katoro-to-Imwelo access road are complete, with compaction continuing. Site clearing and earthworks are advancing, and the construction camp is substantially complete with its water system pressure-tested. The company has no current NI 43-101 mineral resource, mineral reserve or feasibility study supporting its production decision; funding availability and economic and technical failure remain risks.
- Country
- Tanzania
- Commodity
- Au
- Stage
- Construction